Timeline and Milestones for the Measure H1 Facilities Program

2015-16 Development of PUSD Master Plan
2016
November Voter approval of Measure H1
2017
February Selection of HKIT Architects
April Town Hall Meetings, Community Input on Concept Designs
May-September Schematic Design Development, Input from Educators, Staff, Students
September-October Presentation of Schematic Designs to the Community
October-December Design Development
December Selection of General Contractor
Begin Pre-construction Services
2018
January-July Development of Construction Documents
Conduct Constructability Analysis and Value Engineering
July Submittal of STEAM Construction Documents to DSA
September Submittal of Theater Construction Documents to DSA
2019
March Closure of Alan Harvey Theater, Salvage and Abatement Begins
April Demolition of Alan Harvey Theater Begins
June Construction of STEAM building begins
2020
June Demolition of the 10s Building, Construction of new Theater begins
July Completion of STEAM building
August Opening of the STEAM Building, Relocation of Classrooms
2021
Fall Completion and Opening of the new Theater

 

Please note that the precise timing of certain critical steps depends on the timing of approval by California’s Division of State Architect (DSA), the agency which oversees design and construction of public schools, and DSA’s timing is beyond the District’s control.