2015-16 | Development of PUSD Master Plan |
2016 | |
November | Voter approval of Measure H1 |
2017 | |
February | Selection of HKIT Architects |
April | Town Hall Meetings, Community Input on Concept Designs |
May-September | Schematic Design Development, Input from Educators, Staff, Students |
September-October | Presentation of Schematic Designs to the Community |
October-December | Design Development |
December | Selection of General Contractor Begin Pre-construction Services |
2018 | |
January-July | Development of Construction Documents Conduct Constructability Analysis and Value Engineering |
July | Submittal of STEAM Construction Documents to DSA |
September | Submittal of Theater Construction Documents to DSA |
2019 | |
March | Closure of Alan Harvey Theater, Salvage and Abatement Begins |
April | Demolition of Alan Harvey Theater Begins |
June | Construction of STEAM building begins |
2020 | |
June | Demolition of the 10s Building, Construction of new Theater begins |
July | Completion of STEAM building |
August | Opening of the STEAM Building, Relocation of Classrooms |
2021 | |
Fall | Completion and Opening of the new Theater |
Please note that the precise timing of certain critical steps depends on the timing of approval by California’s Division of State Architect (DSA), the agency which oversees design and construction of public schools, and DSA’s timing is beyond the District’s control.